Congleton Link Road: Traffic Management Update April 2021

Congleton Link Road

TEMPORARY TRAFFIC LIGHTS

Sandbach Road, Astbury

There will be temporary 2-way traffic lights in place between the hours of 8.00 am and 4.00 pm to enable sign installation works.

Start Date7 April 2021
Planned Completion Date 7 April 2021


Holmes Chapel Road, Somerford

There will be temporary 2-way traffic lights in place 24 hours a day to allow final works to the new Holmes Chapel Road junction.

Start Date 6 April 2021
Planned Completion Date 9 April 2021


GiantswoodLane, Hulme Walfield

There will be temporary traffic lights in place 24 hours a day to enable completion of landowner access tracks.

Start Date 7 April 2021
Planned Completion Date 9 April 2021

 

ROAD CLOSURES

Holmes Chapel Road, Somerford

We will be imposing an overnight road closure between the hours of 8.00 pm and 6.00 am to enable surfacing works.

Start Date 7 April 2021
Planned Completion Date 7 April 2021


Manchester Road, Congleton

We will be imposing an overnight road closure between the hours of 8.00 pm and 6.00 am to enable surfacing works.

Start Date 8 April 2021
Planned Completion Date 8 April 2021


Macclesfield Road, Eaton

We will be imposing an overnight road closure between the hours of 8.00 pm and 6.00 am to allow surfacing works.

Start Date 9 April 2021
Planned Completion Date 9 April 2021

We would like to thank residents and commuters for their ongoing patience while we deliver this infrastructure programme.