Congleton Link Road: Traffic Management Update March/April 2021

Congleton Link Road

ROAD CLOSURES

Holmes Chapel Road, Somerford

We will be imposing overnight road closures between the hours of 8.00 pm and 6.00 am to enable final surfacing of the new carriageway and roundabout junction.

Start Date: 23 March 2021
Planned Completion Date:  26 March 2021


Manchester Road, Congleton

We will be imposing overnight road closures between the hours of 8.00 pm and 6.00 am to facilitate surfacing works.

Start Date: 30 March 2021
Planned Completion Date: 1 April 2021


Macclesfield Road, Eaton

We will be carrying out an overnight road closure between the hours of 8.00 pm and 6.00 am to allow surfacing works.

Start Date: 29 March 2021
Planned Completion Date: 29 March 2021


TEMPORARY TRAFFIC LIGHTS

Giantswood Lane, Hulme Walfield

There will be temporary traffic lights in place between the hours of 7.00 am and 5.30 pm to allow construction of landowner access tracks.

Start Date: 22 March 2021
Planned Completion Date: 26 March 2021


Sandbach Road, Astbury

There will be temporary traffic lights in place between the hours of 10.00 am and 3.30 pm to enable traffic sign installation and drainage works.

Start Date: 22 March 2021
Planned Completion Date: 26 March 2021

For details of all traffic management or to keep up to date with the project, please visit: www.graham.co.uk/congleton-link-road