ROAD CLOSURES
Back Lane (West), Somerford
The closure will permit the construction of Back Lane (West), including two new roundabouts. There is no access to through traffic along this section of Back Lane, with access to the playing fields being maintained via Holmes Chapel Road.
Date Started 2 September 2019
Planned Completion Date Late 2020
Sandy Lane, between A54 Holmes Chapel Road and A534 Sandbach Road, Somerford
The closure will enable the construction of the mainline carriageway and the new Sandbach Road and Holmes Chapel Road junctions. Sandy Lane will re-open to pedestrians and cyclists when the above works are completed but will remain closed to vehicles.
Date Started 28 May 2019
Planned Completion Date Late 2020
TEMPORARY TRAFFIC LIGHTS
Sandbach Road, Astbury
Temporary traffic lights will be in place between the hours of 7.30 am and 5.30 pm to enable fencing works to be completed.
Date Started 13 October 2020
Planned Completion Date 16 October 2020
Macclesfield Road, Eaton
Temporary traffic lights will be in place 24 hours a day to allow the construction of the new Macclesfield Road junction and tie into the existing carriageway.
Date Started 15 June 2020
Planned Completion Date 18 December 2020
Holmes Chapel Road, Somerford
Temporary traffic lights will be in place between the hours of 7.30 am and 4.30 pm to enable BT cable diversion.
Start Date 12 October 2020
Planned Completion Date 13 October 2020