Congleton Link Road: Traffic Management Update September 2020

Graham traffic management update

OVERNIGHT ROAD CLOSURES

Sandbach Road, Astbury
Overnight road closures will be in place between the hours of 8.00 pm and 5.00 am to enable the final surfacing of the new Sandbach Road junction.

Start Date 1st September 2020
Planned Completion Date 3rd September 2020


ROAD CLOSURES

Back Lane (West), Somerford
The closure will permit the construction of Back Lane (West), including two new roundabouts. There is no access to through traffic along this section of Back Lane, with access to the playing fields being maintained via Holmes Chapel Road.

Date Started 2nd September 2019
Planned Completion Date Late 2020


Sandy Lane, between A54 Holmes Chapel Road and A534 Sandbach Road, Somerford
The closure will enable the construction of the mainline carriageway and the new Sandbach Road and Holmes Chapel Road junctions. Sandy Lane will re-open to pedestrians and cyclists when the above works are completed but will remain closed to vehicles.

Date Started 28th May 2019
Planned Completion Date Late 2020


TEMPORARY TRAFFIC LIGHTS

Sandbach Road, Astbury
Temporary traffic lights will be in place 24 hours a day to allow works to tie in the new Sandbach Road junction to the existing carriageway.

Date Started 10th June 2020
Planned Completion Date 4th September 2020


Macclesfield Road, Eaton
Temporary traffic lights will be in place 24 hours a day to allow works to tie in the new Macclesfield Road junction to the existing carriageway.

Date Started 15th June 2020
Planned Completion Date 2nd October 2020


Holmes Chapel Road, Somerford
Temporary traffic lights will be in place 24 hours a day to enable works to construct the new Holmes Chapel Road junction.

Start Date 14th September 2020
Planned Completion Date 30th October 2020