Congleton Link Road: Traffic Management Update

GRAHAM are the Principal Contractor working on behalf of Cheshire East Council to deliver the Congleton Link Road Project.

Please note below, an update on the road closures, temporary traffic lights and diversions for your information.

ROAD CLOSURE  – Giantswood Lane, Between Westlow Mere and Smithy Lane, Hulme Walfield

The closure will enable the completion of the concrete works to the new structure, carrying out essential utility diversions and resurfacing the realigned carriageway across the bridge.

Started – 21st February 2020

Planned Completion – 9th April 2020


TEMPORARY TWO 2-WAY CARRIAGEWAY – Chelford Road, Between Black Firs Lane and Back Lane, Somerford

To enable the construction of the Chelford Road structure and divert existing services, traffic has been diverted onto a temporary 2-way carriageway.

Temporary Speed Limit – The speed limit has been reduced from national speed limit to 10mph through the works area. The reduction is necessary due to the alignment of the temporary carriageway and interface of construction traffic accessing to and from the works site.

Started – 9th July 2019

For the duration of the Chelford Road overbridge construction


TEMPORARY TRAFFIC LIGHTS – Holmes Chapel Road, Somerford  

Temporary traffic lights will be in place to enable service diversion works and plant crossing Holmes Chapel Road.

Started – 19th February 2020

Planned Completion Date – Late April 2020


ROAD CLOSURE  – Sandy Lane, Between A54 Holmes Chapel Road and A534 Sandbach Road, Somerford

The closure will enable us to access the adjacent land to carry out earthworks, divert drainage and construct the Sandbach Road and Holmes Chapel Road roundabouts. Cyclists and pedestrians will be able to use the route again from Easter 2020.

Started – 28th May 2019

Planned Completion – April 2020


ROAD CLOSURE – Back Lane (West), Somerford

The closure will enable the construction of Back Lane (West) including the new roundabout, There is no access to through traffic along this section of Back Lane, with access to the playing fields been maintained via Holmes Chapel Road. Access to properties on Back Lane is been maintained via Chelford Road.

Started – 2nd September 2019

Planned Completion – Late 2020


TEMPORARY TRAFFIC LIGHTS – Back Lane (East) Congleton

Temporary traffic lights will be in place between the hours of 8.00 am – 4.00 pm to enable drainage surveys to be completed.

Started – 16th March 2020

Planned Completion – 17th March 2020


TEMPORARY TRAFFIC LIGHTS – Macclesfield Road, Eaton

Temporary traffic lights will be in place to enable service diversions and road foundation works to be carried out.

Started –  17th February 2020

Planned Completion – Late June 2020


If you have any questions regarding the information enclosed, please contact us via congletonlink@graham.co.uk